Sunday, April 7, 2013

At Final

The final inspection for occupancy will be on Wednesday April 10.  There is still plenty to do such as installing the glass shower door, the hardware on the kitchen cabinets, & closet rods.  We are expect the back ordered stair nosing to arrive on Monday.  Due to the rain last Friday we delayed the balance of the concrete work until Monday however the other trades also got pushed by the weather so we are now scheduled for Tuesday. The house cleaners were busy at work on the inside this weekend so just a few remaining items to handle.

During the summer months of warmer weather we will be busy painting the shingle walls, belly bands and some of the timber work.

We are all excited to have Dan & Traudi arrive at their new home on Thursday April 11