Friday, November 2nd
Despite the rain a very exciting week, everything is on schedule.  We have the entire basement perimeter walls framed and expect to get a start on the floor joists Saturday Nov 3rd

Thursday, November 1st
Lumber arrived at 9:00 AM on schedule; we started framing just after lunch.

Wednesday October 31st
Completed the back filling, all trenches were closed in just in time for Happy Halloween!

Tuesday, October 30th
Spent the day stripping the forms, outside first so we could complete the back filling then the inside so we could start loading sand.

Monday, October 29th
Pumper truck and concrete trucks all on schedule completed the pour around noon.  The excavator and bobcat arrived around 1:00 PM and we started the moving the dirt.